# Dependency agreement ID / project / as-of: [fill] Provider and receiver: [teams and accepted owners] Deliverable and interface version: [specific usable output] Hard dependency or optional input: [what can proceed without it; what cannot] - Receiver acceptance criteria and verifier: [fill] - Needed-by date and consequence of delay: [fill] - Provider forecast and confidence basis: [fill] - Accepted commitment and source: [fill or explicitly uncommitted] - Integration checkpoint and evidence: [fill] - Required capacity / environment / procurement: [fill] - Change notification and acknowledgement: [owners and response window] - Escalation trigger, decision-maker, latest useful decision date: [fill] - Contingency and when it becomes unavailable: [fill] - Next review: [date/event] - Actual delivery and receiver acceptance: [separate evidence]