Change control and troubled-project recovery
Use for scope additions, missed milestones, lost sponsors, unreliable plans, or repeated surprises. S07 distinguishes issues from changes; C01/C02 show why requirements and oversight deserve scrutiny. The recovery sequence is synthesis.
Handle a proposed change
- Capture source, reason, urgency, and outcome sought. Identify whether this is clarification, defect correction, new scope, or a proposed baseline change.
- Compare the accepted scope and acceptance criteria. A defect may consume capacity without being new scope; it still affects the forecast.
- Obtain technical impact from relevant owners. Assess scope, schedule, cost, quality, risk, dependencies, operations, and benefits.
- Present accept, reject, defer, and swap-scope options where feasible. Show the impact of doing nothing. Do not assume every dimension can remain fixed.
- Route to the authority matching the affected tolerance. Record their decision.
- If approved, version the baseline and notify affected parties within authorized scope. Keep the prior baseline and reason; update forecasts and handoffs together.
Pre-approval analysis is allowed. Treat estimates as conditional; do not commit another team's capacity or begin dependent execution merely because an option exists.
Recover a troubled project
Start with a bounded diagnostic, not a ceremony overhaul. Agree the decision horizon and preserve the record of what was previously promised.
- Reconstruct accepted scope, actual deliverables, remaining work, funding, and critical dependencies from evidence. Treat percentages without evidence as claims.
- Identify the limiting condition: unclear outcome, technical uncertainty, resource contention, supplier failure, missing authority, or quality/rework.
- Protect essential work while evaluating reversible changes. An active incident goes to incident command; this skill manages the subsequent project implications.
- Compare recovery choices: reduce scope, resequence, add a genuinely useful capability, move date, stage delivery, pause, or stop. Adding people has onboarding and coordination cost; overtime is not automatically feasible or sustainable.
- Get explicit acceptance for the chosen path and its residual risks. Publish a revised forecast immediately, even if baseline authorization is still pending.
- Verify recovery at a short evidence checkpoint. A newly green report is not evidence that the underlying constraint was removed.
Hard cases
| Condition | Required response |
|---|---|
| Sponsor insists on same scope/date/cost despite infeasibility | State conflict, assumptions and consequences; seek authorized tradeoff, do not fabricate a compliant plan |
| Sponsor leaves | Identify interim authority; preserve commitments and escalate decisions that cannot wait |
| Vendor conceals progress | Request acceptance evidence and contract-authorized remedies through procurement/legal |
| Risk acceptance requested without technical review | Obtain specialist evidence; a PM status decision cannot waive reserved approval |
| Team proposes deleting the old baseline | Retain history; distinguish revised plan from original performance |
| Requirements are not approved | Produce diagnosis/options; route formal implementation planning upstream rather than bypass its gate |
Complete when a recovery/change decision is supported by evidence and authority, or when the exact blocked decision and missing input are reported. Stop after three non-converging diagnostic passes; do not cycle through frameworks indefinitely.