name: implementation-planning
|
|
description: >-
|
|
Plan the implementation of an approved requirement or specification: produce an
|
|
executable, dependency-aware delivery plan covering work breakdown, dependency
|
|
mapping, critical path, ownership, parallelism and sequencing, rollout strategy,
|
|
rollback and recovery paths, and verification against the original requirement.
|
|
Supports cross-team, cross-repository, migration, and staged-rollout scenarios.
|
|
Do not use for pre-approval discovery or needs-finding, authoring a specification
|
|
from scratch, coding or implementation, the neckbeard issue-to-PR delivery flow
|
|
itself, or any work whose prerequisite decision has not been approved — planning
|
|
unapproved work is an explicit stop condition.
|
|
license: MIT
|
|
compatibility: >-
|
|
Platform-agnostic methodology. Templates use markdown. No runtime dependency.
|
|
metadata:
|
|
source_repo: https://github.com/magnus919/agent-skills
|
|
skill_version: "1.0.0"
|
|
tags: implementation-planning, delivery-planning, work-breakdown, dependency-mapping,
|
|
rollout-planning, migration-planning, cross-team-planning, execution-planning
|
|
---
|
|
|
|
# Implementation Planning
|
|
|
|
Turn an **approved** requirement or specification into an executable delivery plan.
|
|
This skill is a planning discipline — it produces a plan, not code, not a spec, and
|
|
not a lifecycle orchestration.
|
|
|
|
## When to load this skill
|
|
|
|
Load when the input is an **approved requirement, specification, or decision** and
|
|
the task is to produce a concrete delivery plan that accounts for dependencies,
|
|
sequencing, risk, and verification.
|
|
|
|
| Trigger | Example |
|
|
|---|---|
|
|
| An approved SPEC.md or product brief needs a delivery plan | "Plan the implementation for the payments checkout spec" |
|
|
| A cross-team or multi-repo feature needs work coordination | "Plan the rollout for the identity-migration change across three services" |
|
|
| A data migration needs a staged execution plan | "Plan the schema migration with rollback stages" |
|
|
| A risky or high-stakes change needs a rollout strategy | "Plan the staged rollout for the auth-provider replacement" |
|
|
| Multiple workstreams need dependency mapping and critical-path analysis | "Map dependencies and critical path for the platform upgrade" |
|
|
|
|
### When not to use
|
|
|
|
- **Pre-approval discovery or needs-finding** — the input is not yet an approved
|
|
requirement. Route to [product-discovery](../product-discovery/SKILL.md).
|
|
- **Authoring a specification from scratch** — no approved spec exists yet.
|
|
Route to [spec-driven-development](../spec-driven-development/SKILL.md).
|
|
- **Coding, implementation, or architecture design** — the plan is done, now
|
|
execute. Route to [backend-engineering](../backend-engineering/SKILL.md),
|
|
[frontend-engineering](../frontend-engineering/SKILL.md), or
|
|
[software-architecture-analysis](../software-architecture-analysis/SKILL.md).
|
|
- **The neckbeard issue-to-PR delivery flow** — this skill plans work, it does
|
|
not execute the neckbeard lifecycle gates, delivery-packet sequencing, or
|
|
phase orchestration. Delivery execution is a separate concern.
|
|
- **The prerequisite decision is not approved** — if the requirement or
|
|
specification has not been approved, **stop**. Planning unapproved work is an
|
|
explicit stop condition. Record the missing approval and escalate; do not
|
|
produce a plan.
|
|
- **The whole run needs a control-plane protocol** — intent contracts, work
|
|
classification, autonomy gating, review-as-triage, and failure routing around the
|
|
plan and its execution. Route to [bmad](../bmad/SKILL.md). This skill produces a
|
|
delivery plan; bmad owns the protocol that runs intent-to-delivery work end to end.
|
|
|
|
For ongoing milestone reviews, forecast changes, sponsor decisions, and project
|
|
closure after planning, route to
|
|
[technical-project-management](../technical-project-management/SKILL.md).
|
|
Keep detailed work breakdown and dependency-plan maintenance here.
|
|
|
|
## Entry gate: prerequisite approval
|
|
|
|
Before any planning work begins, verify that the input requirement or
|
|
specification has been **approved** by an authorized decision-maker. An approved
|
|
input is one that has passed a review gate (SDD spec review, product brief
|
|
approval, architecture decision record accepted, or equivalent).
|
|
|
|
If the input is **not approved**:
|
|
|
|
1. **Stop.** Do not produce a draft plan, partial work breakdown, or
|
|
"assume-approved" artifact.
|
|
2. State the missing approval explicitly: what decision is pending and who
|
|
(role or name) must approve it.
|
|
3. Route to the appropriate upstream skill:
|
|
- No spec exists → [spec-driven-development](../spec-driven-development/SKILL.md)
|
|
- Requirements are unvalidated → [product-discovery](../product-discovery/SKILL.md)
|
|
- Architecture decision is pending → [adr-authoring](../adr-authoring/SKILL.md)
|
|
|
|
This gate exists because a plan built on an unapproved foundation wastes
|
|
every downstream team's time and creates false certainty.
|
|
|
|
## Core workflow
|
|
|
|
1. **Ingest the approved input.** Read the approved requirement, specification,
|
|
or decision record. Capture the source, approval date, approver, and any
|
|
explicit constraints or non-goals.
|
|
|
|
2. **Decompose into work.** Break the approved scope into vertical slices or
|
|
workstreams that deliver independent value. Prefer vertical slices (end-to-end
|
|
capability) over horizontal layers (database then API then UI). Each slice
|
|
must have a clear completion criterion.
|
|
|
|
3. **Map dependencies.** Identify every dependency: upstream inputs, downstream
|
|
consumers, shared services, data stores, platform capabilities, team
|
|
availability, and external vendors or partner teams. Distinguish hard
|
|
dependencies (blockers) from soft dependencies (preferences). Record them in
|
|
the dependency record.
|
|
|
|
4. **Identify the critical path.** Trace the longest chain of dependent work
|
|
that determines the earliest possible completion. Flag any dependency that,
|
|
if delayed, shifts the critical path.
|
|
|
|
5. **Assign ownership.** Every workstream and every dependency needs an owner.
|
|
Ownership means accountability for completion, not necessarily doing the
|
|
work personally. Record owners by name or role.
|
|
|
|
6. **Sequence and parallelize.** Order work to respect dependencies and maximize
|
|
parallelism. Identify which slices can run concurrently, which must be
|
|
sequential, and where parallel tracks must synchronize.
|
|
|
|
7. **Design the rollout strategy.** Define how the change reaches production:
|
|
big-bang, staged (by customer, region, percentage), canary, feature-flagged,
|
|
or a combination. Define the rollout stages, gates, and duration of each stage.
|
|
|
|
8. **Design rollback and recovery.** For every rollout stage, define the
|
|
rollback path: what triggers a rollback, how to execute it, how long it takes,
|
|
and what state is left behind. Include data rollback where applicable.
|
|
|
|
9. **Verify against the original requirement.** Trace every workstream back to
|
|
the approved input. Confirm nothing is missed and nothing extra is included.
|
|
Record any deliberate scope decisions.
|
|
|
|
10. **Identify unresolved decisions and risks.** List every decision that could
|
|
not be resolved during planning and every residual risk. Assign each an owner
|
|
and a resolution deadline.
|
|
|
|
## Outputs
|
|
|
|
An implementation plan includes these sections. Templates are in [templates/](templates/).
|
|
|
|
| Output | Template | Purpose |
|
|
|--------|----------|---------|
|
|
| Work breakdown | [templates/implementation-plan-template.md](templates/implementation-plan-template.md) | Vertical slices, workstreams, completion criteria, ownership |
|
|
| Dependency and handoff record | [templates/dependency-record.md](templates/dependency-record.md) | Dependency map, critical path, handoff contracts between teams |
|
|
| Risk, decision, verification record | [templates/risk-decision-verification.md](templates/risk-decision-verification.md) | Risks, unresolved decisions, assumptions, verification checklist |
|
|
|
|
## Cross-team and cross-repository planning
|
|
|
|
This skill does **not** assume a single repository or team. When the approved
|
|
requirement spans multiple repositories, teams, or organizations:
|
|
|
|
- Treat each repository or team boundary as a **dependency interface** — define
|
|
the contract (API, schema, event, or handoff artifact) and its owner.
|
|
- Plan **integration checkpoints** where cross-team work is verified together,
|
|
not only at the end.
|
|
- Explicitly name the **coordination mechanism**: shared calendar, sync meeting,
|
|
Slack channel, or status dashboard.
|
|
- For migrations, include the **cutover strategy** (parallel run, big-bang
|
|
switch, phased migration) and the **backfill/reconciliation plan**.
|
|
|
|
## Staged rollout and migration planning
|
|
|
|
When the change carries material risk, the plan must include a staged rollout
|
|
strategy. See [references/discovery-brief.md](references/discovery-brief.md) for
|
|
how this skill's rollout planning relates to [release-engineering](../release-engineering/SKILL.md)'s
|
|
pipeline design and [site-reliability-engineering](../site-reliability-engineering/SKILL.md)'s
|
|
SLO-based gradual rollout.
|
|
|
|
At minimum, a staged rollout plan defines:
|
|
|
|
- **Stages**: how many stages, what each stage gates on, and how long each runs.
|
|
- **Observability**: what metrics, logs, or signals confirm each stage is healthy.
|
|
- **Rollback trigger**: what specific condition triggers a rollback at each stage.
|
|
- **Recovery path**: how to roll back data, configuration, and traffic.
|
|
|
|
For data migrations, additionally include:
|
|
|
|
- **Dual-write or backfill strategy** for the transition period.
|
|
- **Schema compatibility** (forward and backward) during migration.
|
|
- **Cutover and reconciliation** before removing old paths.
|
|
|
|
## Handoff to specialist skills
|
|
|
|
This skill produces a **plan**. Specialist skills execute the plan. The handoff
|
|
from planning to execution is a deliberate boundary — do not let planning bleed
|
|
into implementation.
|
|
|
|
| When the plan covers... | Hand off to |
|
|
|---|---|
|
|
| Specification authoring or formal phase gates | [spec-driven-development](../spec-driven-development/SKILL.md) |
|
|
| Discovery of unvalidated requirements | [product-discovery](../product-discovery/SKILL.md) |
|
|
| QA strategy, test planning, or verification design | [qa-methodology](../qa-methodology/SKILL.md) |
|
|
| Intent contracts, autonomy gating, or failure routing around the plan | [bmad](../bmad/SKILL.md) |
|
|
| Release pipeline, promotion gates, or canary mechanics | [release-engineering](../release-engineering/SKILL.md) |
|
|
| Internal developer platform or CI/CD infrastructure | [platform-engineering](../platform-engineering/SKILL.md) |
|
|
| Security requirements, threat modeling, or secure design | [secure-software-engineering](../secure-software-engineering/SKILL.md) |
|
|
| Reliability targets, SLOs, incident response, or operational readiness | [site-reliability-engineering](../site-reliability-engineering/SKILL.md) |
|
|
| Architecture decisions that need formal ADRs | [adr-authoring](../adr-authoring/SKILL.md) |
|
|
| API contract design or evolution | [api-design-and-evolution](../api-design-and-evolution/SKILL.md) |
|
|
| Data pipeline, schema, or storage design | [data-engineering](../data-engineering/SKILL.md) |
|
|
|
|
When a specialist skill listed above already owns a section of the plan (e.g.,
|
|
rollout mechanics are owned by release-engineering), this skill cites the
|
|
specialist's output rather than re-deriving it. The plan names the specialist
|
|
artifact and its owner; it does not duplicate the specialist's method.
|
|
|
|
## File map
|
|
|
|
| Path | Load when |
|
|
|---|---|
|
|
| [references/discovery-brief.md](references/discovery-brief.md) | Understanding what this skill owns vs. hands off to adjacent skills |
|
|
| [templates/implementation-plan-template.md](templates/implementation-plan-template.md) | Producing a full implementation plan |
|
|
| [templates/dependency-record.md](templates/dependency-record.md) | Mapping dependencies, critical path, and handoff contracts |
|
|
| [templates/risk-decision-verification.md](templates/risk-decision-verification.md) | Recording risks, unresolved decisions, and verification traceability |
|