name: technical-project-management
|
|
description: >-
|
|
Manage technical projects from initiation through delivery and closure: choose
|
|
and tailor predictive, iterative, Scrum, flow-based, or hybrid approaches;
|
|
coordinate teams and vendors; track milestones, risks, issues, dependencies,
|
|
forecasts, scope changes, and recovery. Use when a team has no project manager,
|
|
a TPM needs decision-ready analysis, a project is slipping, or commitments and
|
|
handoffs need coordination. Use `technical-program-management` instead when
|
|
multiple related projects, teams, vendors, shared capacity, or benefits must be
|
|
coordinated toward one outcome. Adapt depth to the user's expertise. Do not use for
|
|
a standalone coding task, product discovery or strategy, only writing an
|
|
implementation plan, only diagnosing Kanban flow, operating a ticket tool,
|
|
incident command, or a release go/no-go decision; route those to specialists.
|
|
license: MIT
|
|
compatibility: >-
|
|
Host-neutral methodology and Markdown templates. Optional read-only schedule
|
|
analysis requires Python 3.10+ standard library; no credentials or network.
|
|
---
|
|
|
|
# Technical Project Management
|
|
|
|
Help a team make and maintain credible delivery commitments. Start at the user's
|
|
current decision; do not restart a healthy project or impose a new methodology.
|
|
|
|
## First move
|
|
|
|
Read existing project artifacts before asking questions. Identify the outcome,
|
|
current phase, immediate decision, decision-maker, constraints, and evidence gaps.
|
|
Infer experience from the request and artifacts; ask about preference only if it
|
|
matters. For teams without a PM, provide a small usable working system and explain
|
|
unfamiliar concepts in context. For experienced TPMs, lead with the delta, options,
|
|
recommendation, and decision needed; omit introductory lessons.
|
|
|
|
### Choose the entry point
|
|
|
|
| Starting condition | First action | Primary output |
|
|
|---|---|---|
|
|
| New or inherited project with unclear mandate | Read [Engagement and initiation](references/engagement-and-initiation.md) | Proposed brief with authority and evidence gaps |
|
|
| Approved work with a delivery method but weak control | Read [Control and communication](references/control-and-communication.md) | Current control record and decision brief |
|
|
| Slipping date, cost, scope, or dependency | Read [Forecasting and schedule analysis](references/forecasting.md) and [Change and recovery](references/change-and-recovery.md) | Conditional forecast and recovery options |
|
|
| Cross-team, supplier, or mixed-method handoff | Read [Hybrid and dependencies](references/hybrid-and-dependencies.md) | Dependency agreement and acceptance evidence |
|
|
| Delivered work, retirement, or decommissioning with unresolved ownership or benefits | Read [Closure and transition](references/closure-and-transition.md) | Conditional closure, accepted transition, or decommissioning record |
|
|
| Technical uncertainty needs staged learning | Read [Adaptive delivery](references/adaptive-delivery.md) | Evidence-backed decision among PoC, prototype, pilot, or stop; none alone proves production readiness |
|
|
| Forecast, deadline, or resource-feasibility question | Read [Forecasting and schedule analysis](references/forecasting.md) | Conditional forecast stating model, assumptions, capacity, and feasibility limits |
|
|
| Material risk, issue, assumption, or decision needs control | Read [Control and communication](references/control-and-communication.md) | Record with owner, signal/trigger, response, authority, and next review |
|
|
| A supplier or team handoff lacks readiness or acceptance evidence | Read [Hybrid and dependencies](references/hybrid-and-dependencies.md) | Agreement with provider, receiver, definition of ready, evidence, fallback, and escalation |
|
|
|
|
Do not call a desired date a commitment, a forecast an acceptance, or a diagnostic brief an approved plan.
|
|
|
|
> Before proposing a commitment, identify who can authorize scope, dates, capacity, acceptance, and external communication. Mark each as accepted, proposed, unknown, or disputed. Read-only diagnosis may proceed; external updates require authorization.
|
|
|
|
## Operating loop
|
|
|
|
1. Establish mandate and authority; separate approved commitments, forecasts,
|
|
assumptions, and unknowns. A diagnostic or options brief can precede approval;
|
|
do not turn it into an approved implementation plan.
|
|
2. Select the smallest adequate management approach. Preserve effective existing
|
|
practices and specify any changed decision rights, cadence, and handoffs.
|
|
3. Reuse the implementation plan and maintain milestones, dependency commitments,
|
|
remaining work, resource availability, risks, issues, and decisions.
|
|
4. Compare evidence with the baseline and tolerances. Investigate contradictions;
|
|
missing evidence means unknown, not green. Surface forecast changes immediately
|
|
when material; do not wait for a scheduled report.
|
|
5. Present feasible options when scope, capacity, cost, or dates conflict. Keep the
|
|
baseline history; an authorized change is not permission to hide prior variance.
|
|
6. Close only on acceptance and explicit residual ownership. Distinguish project
|
|
closure, release readiness, service operation, and later benefit realization.
|
|
|
|
## Reference routing
|
|
|
|
Read only what the current task requires. Each reference includes applicability,
|
|
procedures, failure signals, and an observable exit.
|
|
|
|
A multi-project initiative with a shared outcome, cross-project dependencies, or
|
|
program-level benefits belongs to `technical-program-management`; a single bounded
|
|
project remains here.
|
|
|
|
| Decision phase / situation | Read | Exit artifact or evidence |
|
|
|---|---|---|
|
|
| New or inherited project, no PM, expert collaboration | [Engagement and initiation](references/engagement-and-initiation.md) | Proposed brief with mandate, authority, and evidence gaps |
|
|
| Choosing or questioning a methodology | [Method selection](references/method-selection.md) | Approach decision with adaptations and revisit trigger |
|
|
| Predictive planning, stages, tolerances, fixed constraints | [Predictive and stage governance](references/predictive-and-stages.md) | Baseline, tolerances, and gate evidence |
|
|
| Scrum, iteration, incremental delivery, discovery uncertainty | [Adaptive delivery](references/adaptive-delivery.md) | Learning/increment evidence and inspect/adapt decision |
|
|
| Flow, shared specialists, critical chain, appetite-based work | [Flow and constrained capacity](references/flow-and-capacity.md) | Capacity/WIP or appetite decision with owner |
|
|
| Mixed methods, cross-team or vendor interfaces | [Hybrid and dependencies](references/hybrid-and-dependencies.md) | Dependency agreement and interface acceptance evidence |
|
|
| Estimates, forecasts, budgets, schedule model | [Forecasting and schedule analysis](references/forecasting.md) | Conditional forecast with assumptions and feasibility limits |
|
|
| Weekly control, stakeholder disagreement, escalations | [Control and communication](references/control-and-communication.md) | Status/update or decision brief with next checkpoint |
|
|
| Scope changes, troubled projects, recovery | [Change and recovery](references/change-and-recovery.md) | Change/recovery record preserving the baseline |
|
|
| Acceptance, cancellation, operational handoff | [Closure and transition](references/closure-and-transition.md) | Closure or transition record with residual owners |
|
|
| Real examples or transferability checks | [Case studies](references/case-studies.md) | Source-limited analogy, not a guarantee |
|
|
| Research provenance, edition, evidence limits | [Source index](references/source-index.md) | Traceable evidence ledger |
|
|
| Skill purpose, coverage, research decisions | [Research brief](references/research-brief.md) | Coverage and limitation record |
|
|
| Validation scope and behavioral evaluation protocol | [Evaluation guide](references/evaluation-guide.md) | Reproducible evaluation record |
|
|
|
|
## Templates and calculation
|
|
|
|
Adapt existing project documents rather than creating parallel sources of truth.
|
|
Use only artifacts that answer a current decision.
|
|
|
|
| Need | Artifact |
|
|
|---|---|
|
|
| Establish mandate and working agreements | [Project brief](templates/project-brief.md) |
|
|
| Explain method choice and adaptation | [Approach decision](templates/approach-decision.md) |
|
|
| Maintain milestones and evidence | [Project control record](templates/project-control.md) |
|
|
| Coordinate a supplier or receiving team | [Dependency agreement](templates/dependency-agreement.md) |
|
|
| Report a change and ask for a decision | [Status and decision brief](templates/status-and-decision.md) |
|
|
| Assess scope changes or recovery options | [Change and recovery record](templates/change-and-recovery.md) |
|
|
| Accept, cancel, or transfer ownership | [Closure record](templates/closure-record.md) |
|
|
| Calculate a small dependency network | [Example schedule](templates/schedule-example.json) |
|
|
|
|
Run `python3 scripts/schedule.py --input templates/schedule-example.json --json`
|
|
from this skill's directory when dependency arithmetic helps. Read forecasting
|
|
first: the result is an unconstrained earliest schedule, not a commitment or a
|
|
resource-leveled plan. The script only reads input and writes stdout/stderr.
|
|
Run `python3 -m unittest discover -s scripts -p 'test_*.py'` for its tests.
|
|
|
|
## When not to use
|
|
|
|
- A coding fix or architecture design: use the applicable engineering skill.
|
|
- Validating needs or choosing product investments: use
|
|
[product-discovery](../product-discovery/SKILL.md) or
|
|
[product-roadmapping-and-portfolio](../product-roadmapping-and-portfolio/SKILL.md).
|
|
- Only decomposing an approved requirement: use
|
|
[implementation-planning](../implementation-planning/SKILL.md).
|
|
- Detailed board, WIP, or service-flow diagnosis: use
|
|
[kanban-guru](../kanban-guru/SKILL.md).
|
|
- Shaping a bounded product bet: use [product-shaping](../product-shaping/SKILL.md).
|
|
- Product-wide decision rights: use
|
|
[product-operations-and-governance](../product-operations-and-governance/SKILL.md).
|
|
- Executive-office support: use
|
|
[chief-of-staff-methodology](../chief-of-staff-methodology/SKILL.md).
|
|
- Release mechanics or launch approval: use
|
|
[release-engineering](../release-engineering/SKILL.md) and
|
|
[production-readiness](../production-readiness/SKILL.md). This skill may track project implications after that decision, but does not approve the release.
|
|
- Live incident command: use
|
|
[site-reliability-engineering](../site-reliability-engineering/SKILL.md).
|
|
- Ticket operations alone: use [jira](../jira/SKILL.md) or
|
|
[linear](../linear/SKILL.md). Use [financial-modeling](../financial-modeling/SKILL.md)
|
|
for financial model construction, and [legal-strategy](../legal-strategy/SKILL.md)
|
|
for contract interpretation.
|
|
|
|
## Authority and completion
|
|
|
|
This methodology prepares decisions. It does not invent stakeholder consent,
|
|
assign accepted commitments on someone else's behalf, or approve risk. Updating
|
|
external project systems or sending communications changes external state:
|
|
|
|
> Confirm the target, scope, and rollback path before acting. Read-only discovery may proceed without confirmation.
|
|
|
|
Apply existing session authorization; do not ask repeatedly for the same scope.
|
|
Destructive actions need an explicit directive. Keep prepared drafts visibly distinct
|
|
from issued communications. Do not monitor people or turn activity counts into
|
|
individual performance judgments.
|
|
|
|
Complete a requested management cycle when the artifact or update is delivered,
|
|
claims have evidence or explicit uncertainty, and unresolved decisions have an
|
|
accountable route and next review trigger. Do not imply ongoing monitoring without
|
|
an authorized mechanism. If three diagnostic passes yield no new evidence, stop
|
|
with the missing input and affected decision; do not manufacture certainty.
|