# Hybrid delivery and dependency coordination
|
|
|
|
Use when teams, vendors, procurement, hardware, or governance work on different
|
|
cadences. Basis: S01/S06 support tailoring; C03 supplies a real coordination
|
|
example. The interface procedure below is this skill's synthesis.
|
|
|
|
## Define a hybrid precisely
|
|
|
|
Name which work follows which approach, why, and who owns each interface. A
|
|
monthly sponsor decision can coexist with continuous software delivery; it must
|
|
not secretly require every team to wait for a monthly release. Conversely, a
|
|
sprint review cannot override a required external certification.
|
|
|
|
Maintain one authoritative milestone/decision view. Team backlogs can differ;
|
|
project commitments cannot contradict each other without a visible unresolved
|
|
issue. Do not impose a shared sprint length merely to simplify reporting.
|
|
|
|
## Dependency agreement
|
|
|
|
For each material dependency record: provider, receiver, deliverable and version,
|
|
acceptance evidence, needed-by date, provider forecast, accepted commitment,
|
|
confidence basis, review date, escalation owner, and fallback. A provider saying
|
|
"we'll try" is a forecast or aspiration, not a commitment.
|
|
|
|
1. Ask the receiver what usable input is needed, not just which team is blocking.
|
|
2. Validate whether it is a hard dependency. A mock may permit development but not
|
|
production acceptance; document both boundaries.
|
|
3. Confirm the provider's scope and capacity. Include procurement lead time,
|
|
reviews, security, test environments, and customer participation.
|
|
4. Schedule an integration checkpoint before the final milestone. Agree how a
|
|
failed handoff changes the forecast and who decides the response.
|
|
5. Track interface changes and receiver acknowledgement. A delivered artifact is
|
|
not an accepted handoff until the receiving party can use it as agreed.
|
|
|
|
## Vendor and distributed-team cases
|
|
|
|
| Problem | Response |
|
|
|---|---|
|
|
| Fixed-price vendor with evolving software needs | Identify contractual acceptance/change process; assess options with procurement/legal rather than interpreting rights yourself |
|
|
| Vendor dates lag the project need | Record date gap and latest decision point for contingency; escalate before the fallback becomes impossible |
|
|
| Shared environment unavailable | Treat environment capacity as a dependency, with a specific reservation owner |
|
|
| Time-zone handoffs add a day per question | Use an async decision brief, clear response window, and backup decision-maker |
|
|
| Two teams claim contract ownership | Separate authoring, approval, and acceptance responsibilities; route unresolved authority to the sponsor |
|
|
| Several projects compete for one team | Surface program/portfolio arbitration; do not allocate another project's capacity unilaterally |
|
|
|
|
## Worked boundary (hypothetical)
|
|
|
|
A vendor provides a certified device in week 8; software teams iterate fortnightly.
|
|
The project has interface test evidence due in week 5 and integrated acceptance in
|
|
week 9. If certification moves to week 10, successful software sprints do not keep
|
|
the project green. Present a revised integration forecast, impact on commitments,
|
|
and an authorized fallback decision. A simulator retires interface uncertainty but
|
|
does not replace device certification.
|
|
|
|
Complete when critical handoffs have accepted owners, evidence, dates, and escalation
|
|
paths, or their absence is explicitly blocking the affected commitment.
|