# Assembly and verification
|
|
|
|
Acceptance is a chain from physical workmanship to observed behavior.
|
|
|
|
## Unpowered inspection
|
|
|
|
Inspect orientation, reference designators, solder bridges, wetting, lifted
|
|
pads, connector seating, strain relief, and selectable pull-ups/address links.
|
|
Check intended continuity and rail-to-rail/signal shorts with power removed;
|
|
discharge capacitors first. Compare the assembly against the current BOM,
|
|
schematic, layout, and assembly revision. Photograph or annotate anomalies.
|
|
|
|
## Controlled first power
|
|
|
|
Use a current-limited source when appropriate. Start with loads disabled and
|
|
measure rail voltage, startup/steady current, reset behavior, and temperature.
|
|
Add peripherals and outputs one at a time. Verify idle levels before enabling
|
|
drivers. A current limit is a protective aid, not a replacement for a supply
|
|
budget or fault analysis.
|
|
|
|
## Functional acceptance
|
|
|
|
Require an identity-level check for each bus device, a known input/output
|
|
response, and documented reset and power-cycle behavior. For I2C, retain the
|
|
raw capture or transaction log, address convention, measured rise time,
|
|
effective pull-up, and recovery result. For analog or timed behavior, record
|
|
calibration/reference, sample conditions, tolerance, and measurement setup.
|
|
|
|
Repeat critical tests after mechanical handling and any relevant thermal or
|
|
power condition. Record exact board/component/firmware revisions and every
|
|
open risk. “It worked once” is not an acceptance criterion.
|
|
|
|
| Failure at acceptance | Containment | Evidence needed before release |
|
|
|---|---|---|
|
|
| Rail short or excess startup current | power off; isolate branch; inspect orientation/bridges | corrected inspection and current trace |
|
|
| Correct rail, wrong idle state | disable load; check reset pulls and external straps | schematic-to-measured state comparison |
|
|
| Bus responds but identity fails | stop application writes; preserve raw capture | documented identity read and address convention |
|
|
| Intermittent after handling | repeat visual/continuity and capture under movement | reproducible mechanical condition or closure |
|
|
| Recovery leaves line low | keep controller quiescent; reset/power-cycle holder | before/after line capture and owner |
|
|
|
|
Release requires a named disposition for every failure: fixed and retested,
|
|
accepted with an explicitly bounded risk, or blocked pending an artifact or
|
|
measurement. A passing functional test cannot waive an unresolved electrical
|
|
limit.
|
|
|
|
The acceptance artifact is complete when another operator can reproduce the
|
|
test, distinguish design evidence from instrument setup, and see the rollback
|
|
or recovery path for every state-changing test.
|
|
|
|
## Acceptance stage record
|
|
|
|
At inspection, record component reference, defect class, image identifier, and
|
|
disposition. At unpowered test, record meter mode, lead resistance, test points,
|
|
and measured values; a continuity beep alone is insufficient. At first power,
|
|
record current-limit setting, source voltage, startup peak, steady current,
|
|
rail ripple, reset reason, and temperature. At functional test, record stimulus,
|
|
expected response, actual response, repeat count, and environmental condition.
|
|
|
|
For a soldered I2C connector, visual inspection may show correct pin placement,
|
|
while end-to-end resistance proves only a low-current path. Far-end idle voltage,
|
|
rise time with the actual probe, and identity readback establish separate facts.
|
|
If those disagree, retain all results and localize the defect instead of marking
|
|
the connector “passed.”
|
|
|
|
Release is a disposition, not a checkbox: passed and repeatable, accepted with
|
|
an explicitly bounded risk and owner, or blocked pending evidence. Rework must
|
|
repeat the tests affected by the rework.
|