# Real-world cases and transfer limits
|
|
|
|
Use when testing a proposed practice against experience. Source IDs resolve in the
|
|
source index. Findings are paraphrased narrowly; proposed controls are our
|
|
interpretation. These are illustrative cases, not a controlled comparison of methods.
|
|
|
|
## Healthcare.gov: visible progress without reliable control
|
|
|
|
**Context and evidence:** The 2013 marketplace launch involved multiple systems and
|
|
contractors. GAO's 2014 audit (C01) connected changing requirements and oversight
|
|
gaps with increased costs and schedule slippage. Its 2015 review (C02) identified
|
|
incomplete testing, weak requirements management, and an unreliable schedule; later
|
|
recommendation updates document corrective actions.
|
|
|
|
**Our inference:** A dashboard cannot compensate for uncertain scope and missing
|
|
integration evidence. **Proposed control:** reconcile current scope, remaining work,
|
|
and acceptance evidence before assigning project health. Require a specific decision
|
|
when an external deadline and demonstrated readiness conflict.
|
|
|
|
**Transfer limit:** This does not establish that a particular framework caused the
|
|
failure or that a startup needs federal acquisition governance. **Test question:**
|
|
what evidence could make you withdraw today's green status?
|
|
|
|
## GitHub's MySQL upgrade: coordination before cutover
|
|
|
|
**Evidence (C03):** GitHub reports upgrading more than 1,200 hosts, with preparation
|
|
and execution taking over a year across teams and without impact to its SLOs. Its
|
|
account describes compatibility testing, a rolling calendar and issue checklists
|
|
for app/database coordination, gradual upgrades, and rollback preparation.
|
|
|
|
**Our inference:** Prerequisite readiness and handoff agreements belong in the
|
|
project plan. **Proposed control:** track receiver acceptance and rollback evidence
|
|
alongside each scheduled migration wave, with a decision owner for conflicts.
|
|
|
|
**Transfer limit:** This is self-reported success in a specific architecture. Do
|
|
not copy its database topology, rollback assumptions, or duration to another system.
|
|
**Test question:** can each team identify the evidence needed before its next handoff?
|
|
|
|
## Mars Climate Orbiter: interfaces and escalation
|
|
|
|
**Evidence (C04):** NASA's retrospective briefing identifies a units mismatch plus
|
|
inadequate interface verification, missing end-to-end testing evidence, incomplete
|
|
communication of navigation concerns, and readiness weaknesses around the 1999 loss.
|
|
|
|
**Our inference:** Naming an interface is insufficient unless someone verifies it
|
|
and unresolved concerns reach an accountable decision-maker. **Proposed control:**
|
|
include contract version, receiving-team verification, escalation trigger, and
|
|
fallback readiness in dependency agreements.
|
|
|
|
**Transfer limit:** A spacecraft's irreversibility differs from a reversible web
|
|
release. The lesson is proportional verification and escalation, not treating every
|
|
software update as a mission launch. **Test question:** who must act if the receiving
|
|
team sees an unexplained mismatch?
|
|
|
|
## GOV.UK: the end of migration is a new operating context
|
|
|
|
**Evidence (C05):** GDS's 2015 account reports completing the single-domain transition
|
|
and shifting priorities away from organizations' migration timetables toward
|
|
supporting and improving the service, with team and goal changes.
|
|
|
|
**Our inference:** A successful migration milestone does not settle ongoing
|
|
ownership or service priorities. **Proposed control:** obtain accepted operational
|
|
ownership and a benefits-review handoff as part of project closure.
|
|
|
|
**Transfer limit:** A leadership account does not independently verify all benefits
|
|
or prove its organization design fits another team. **Test question:** what changes
|
|
in ownership and decision cadence after the project team disbands?
|
|
|
|
## Using cases responsibly
|
|
|
|
Compare uncertainty, scale, reversibility, incentives, authority, and dependency
|
|
structure before transferring a lesson. Seek a counterexample or local evidence
|
|
that would invalidate the analogy. Do not manufacture a small-team case by shrinking
|
|
one of these organizations. Hypothetical worked examples in other references are
|
|
labeled explicitly and are not part of the field evidence.
|