# Forecasting, cost, and schedule analysis
|
||
|
||
Use for "when will it finish?", date confidence, critical-path changes, or cost
|
||
exposure. S04 supports the need for credible schedule logic and schedule-risk
|
||
analysis. The model-selection procedure and calculator are original implementations.
|
||
|
||
## Match the model to the evidence
|
||
|
||
- Stable, dependent deliverables: inspect the network and remaining durations.
|
||
- Repeated comparable work: use historical throughput/flow forecasting through
|
||
kanban-guru, preserving its assumptions and observation window.
|
||
- Novel research or unstable scope: offer scenarios and an early learning gate.
|
||
Do not manufacture probability distributions from guesses.
|
||
- Material funding decisions: maintain actual cost plus estimate to complete;
|
||
route model construction to financial-modeling.
|
||
|
||
Keep **baseline commitment**, **current forecast**, **required deadline**, and
|
||
**actual acceptance** separate. A forecast is conditional; a commitment is an
|
||
accountable decision. More decimal places do not improve weak inputs.
|
||
|
||
## Forecast review
|
||
|
||
Capture as-of date, remaining scope, done criteria, available capacity, exclusions,
|
||
model, assumptions, and sources. Review calendar effects, parallelism, scarce
|
||
skills, rework, supplier waits, and uncertainty correlations. If all paths depend
|
||
on the same test lab, they do not fail independently.
|
||
|
||
For probabilistic forecasts, state the sample, comparable conditions, simulation
|
||
method, confidence level, and events outside the model. Small or changing samples
|
||
are limitations, not proof of a precise percentile. Separate forecast calibration
|
||
from whether a target was politically accepted. Revisit after material scope or
|
||
capacity changes; compare forecast with actual delivery to learn.
|
||
|
||
For budgets, distinguish approved funding, actuals, committed but uninvoiced spend,
|
||
remaining estimate, and contingency. Avoid counting a purchase in both actuals and
|
||
commitments. Earned value is useful only with a credible time-phased cost baseline
|
||
and objective earning rules; ticket percentages are not automatically earned value.
|
||
Do not compare SPI to calendar-day delay. Record financial assumptions for review.
|
||
|
||
## Read-only schedule helper
|
||
|
||
Run from the skill root:
|
||
|
||
```sh
|
||
python3 scripts/schedule.py --input templates/schedule-example.json --json
|
||
python3 -m unittest discover -s scripts -p 'test_*.py'
|
||
```
|
||
|
||
Input is a JSON object with `schema_version: 1`, `unit: "working_days"`, and
|
||
`tasks`: 1–500 objects. Each task has a unique non-empty `id`, nonnegative finite
|
||
`duration` (elapsed working days, not person-days), and `depends_on` list. Optional
|
||
`resource` identifies a single exclusive resource; it detects overlapping demand
|
||
but does not schedule it. Optional `deadline` is a nonnegative working-day offset
|
||
from project start. No dates, calendars, lags, partial progress, or unknown fields
|
||
are accepted. Use zero-duration tasks for milestones; they occupy no resource time.
|
||
|
||
The algorithm topologically sorts finish-to-start dependencies, performs a forward
|
||
pass for earliest times and a backward pass against the unconstrained finish for
|
||
float. It returns all zero-float task IDs (which may span multiple paths), finish
|
||
offset, deadline gap, and resource overlaps (first 100 pairs plus total count and truncation flag).
|
||
`deadline_gap = finish - deadline`;
|
||
positive is late. Float is relative to modeled finish, not the requested deadline.
|
||
|
||
This is a lower bound under precedence constraints and assumed durations. It is
|
||
not a resource-leveled schedule, Monte Carlo model, working-calendar converter,
|
||
critical-chain implementation, or completion promise. A resource warning means the
|
||
earliest dates conflict; resequence in the source plan and recalculate. Other
|
||
resource conflicts can exist even if no resource labels were supplied.
|
||
|
||
The script performs no network calls and mutates no files. JSON goes to stdout;
|
||
invalid input errors go to stderr with exit 2. Success is exit 0, including a late
|
||
forecast: lateness is data, not malformed input. Boundaries: 1 MB input, at most
|
||
500 tasks, finite aggregate duration no larger than one million working days.
|
||
|
||
## Interpretation example
|
||
|
||
Design takes 2 days. Build (3 days) and review preparation (1 day) depend on design.
|
||
Acceptance (1 day) requires both. Finish is day 6; design, build, and acceptance
|
||
have zero float; review preparation has 2 days float. If build and review preparation
|
||
need the same exclusive person, the apparent parallel schedule conflicts. Do not
|
||
report day 6 as a feasible commitment without resolving that conflict.
|
||
|
||
Complete when the forecast and its uncertainty are stated, contradictions are
|
||
visible, and the decision-maker understands what must change to meet the target.
|
||
|
||
For this small example, one exclusive specialist must do build and review
|
||
preparation serially: 2 + 3 + 1 + 1 = 7 working days. A second specialist restores
|
||
the dependency-only day 6; it cannot by itself achieve day 5. For a small network,
|
||
show such a feasible sequence explicitly; do not imply the helper leveled it.
|