# Select and tailor the approach
|
|
|
|
Use when choosing a method or when delivery pain suggests the current method no
|
|
longer fits. Basis: S01's fit-for-purpose argument and S06's distinction among
|
|
delivery approaches. This decision procedure is a practical synthesis, not a
|
|
certification decision tree or a ranking of methodologies.
|
|
|
|
## Diagnose before prescribing
|
|
|
|
Inspect six things: requirement stability, technical uncertainty, ability to
|
|
release partial value, cost of reversing a decision, external timing constraints,
|
|
and actual team autonomy/capacity. Also identify mandatory governance. A team
|
|
calling its work agile does not prove these conditions hold.
|
|
|
|
Default to the team's existing adequate approach. Change it only to address an
|
|
observed problem. Do not use a weighted score to hide a veto condition such as an
|
|
unavailable safety approver or impossible vendor lead time.
|
|
|
|
| Conditions | Candidate | First check | Failure signal / response |
|
|
|---|---|---|---|
|
|
| Known deliverable, stable interfaces, expensive irreversible steps | Predictive with staged decisions | Is the dependency plan feasible with actual resources? | Repeated late changes: shorten planning horizon and add discovery |
|
|
| Need to learn what works through feedback | Iterative | Who evaluates the experiment and when? | No feedback access: resolve it before committing more cycles |
|
|
| Useful components can be accepted separately | Incremental | Does each increment work end to end? | Layer-only milestones: redefine around usable capability |
|
|
| Cohesive team, clear product authority, regular inspect/adapt cycle | Scrum | Can the team protect a goal and meet a shared quality bar? | Many unrelated interruptions: fix intake/capacity, consider flow |
|
|
| Variable arrival, support work, aging queues | Flow-based/Kanban | Are start/finish and capacity policies explicit? | WIP growth: investigate bottleneck before adding work |
|
|
| Scarce resources repeatedly delay otherwise independent work | Critical-chain lens | Are resource contention and readiness visible? | Treating buffers as hidden padding: make them explicit and owned |
|
|
| Bounded product opportunity, discretionary scope, protected capacity | Appetite-based/Shape Up | Can leadership actually protect the bet? | Mandatory scope exceeds appetite: reshape or choose a different model |
|
|
| Hardware/vendor stages plus evolving software | Hybrid | Who accepts the cross-method interfaces? | Two conflicting plans: establish one milestone/decision record |
|
|
|
|
Predictive is a planning approach; Scrum is a framework; critical path and critical
|
|
chain are scheduling techniques; PRINCE2 is a project management method; Kanban
|
|
manages flow. They are not interchangeable alternatives at one abstraction level.
|
|
Stage governance can coexist with iterative delivery. Iterative learning does not
|
|
necessarily produce a releasable increment; incremental delivery need not entail
|
|
high uncertainty. Do not call all of these "agile" without qualification.
|
|
|
|
## Make the choice actionable
|
|
|
|
Write an approach decision: observed conditions, selected approach, nearest rejected
|
|
alternative, who decides scope and dates, cadence, required evidence, and revisit
|
|
trigger. Define the first inspection point. Explain only the tradeoff the user
|
|
needs, rather than reciting the whole matrix.
|
|
|
|
Example (hypothetical): a device project has a long-lead board order and uncertain
|
|
calibration software. Use a staged procurement decision for hardware and short
|
|
software learning cycles, tied to an integrated prototype acceptance milestone.
|
|
Do not let software sprint completion imply the device is ready for certification.
|
|
|
|
## Edge cases and exit
|
|
|
|
Mandatory organizational methods constrain tailoring: surface a justified exception
|
|
request rather than quietly replacing the method. A small team does not need
|
|
separate meetings for every practice. A multi-project program may need an additional
|
|
benefits and governance owner; expose that need instead of promising this skill
|
|
replaces enterprise program management.
|
|
|
|
Complete when one approach and its adaptations address the diagnosed conditions,
|
|
its coordination contract is explicit, and a review trigger exists.
|